Carol Stamper, Chief Operations Officer
The Roof Top Replacement Units Project was bid on April 7, 2016. Staff recommends the approval of this project to the lowest competent bidder, Thermal Conditioning Inc. in the amount of $213,518.93. The contractor agrees to replace the existing 16 Package Roof Top Units with like units. The contractor will provide the labor, services, equipment, and materials needed to install pumps and controls All work is to be performed in accordance with the standard terms and conditions outlined in the contract.
MWSBE: 0%