Overall Budget: $15,300,000.00
|
CMS Project Manager: Chip Lofton
|
| Architect: ADW Architects |
| General Contractor: Matthews Construction Co., Inc. |
Site Designer: Site Solutions
|
Scope of Work A new 39 classroom elementary school. This project relieves overcrowding at Torrence Creek ES.
|
Progress Roofing and window installation is still ongoing and expected to finish in the next couple of weeks. Gypsum wall board hanging has begun on the first floor. Load bearing CMU is 100% complete and brick veneer is approximately 95% complete.
|